PILE TEST & INSTALLATION CAMPAIGN

IN SHORT
VESSEL MV Lone
CARGO 9 piles, 36 x 1.4 m dia – weight up to 47 t
WEIGHT 165 t (piling frame and hydro hammer)
LOCATION German sector of Baltic Sea, north east of the island of Rügen
PROJECT Wikinger Wind Farm – Test Pile Campaign
SPECIALS
  • Installation of 9 test piles at 3 locations at water depths of up to 40 m
  • Project equipment: hydraulic hammer, lifting tools, WROV, sensor equipment, survey and pile cutting spread, marine mammal observers
  • Installation of pile guide frame at up to 40 m depth in DP mode
PROJECT SUMMARY

INSTALLATION OF 9 TEST PILES AT 3 LOCATIONS AT WATER DEPTHS OF UP TO 40 M

When Type 183 HLV Lone was engaged in a Taiwanese offshore pile load test project for an offshore wind farm, it took another four vessels to mobilise her. This project took more than our best efforts and engineering capabilities – it also required ingenuity and a significant crane modification to achieve our goal. HLV Lone was hired to perform pile installation and testing work as part of the pre-piling phase of the project.

To realize the project, we launched a substantial preparation phase: A Fly-Jib extension was designed, manufactured, and installed, providing up to 23 m of extra jib length. Furthermore, temporary living quarters (TLQs) and additional lifeboats to house up to 100 people that would be onboard during the project were installed and HLV Lone had to change its certification from a cargo vessel to become a special purpose ship (SPS).

Want to know more?

Contact our team on
solutions@jumbo-sal-alliance.com

Send project by email

    RELATED #OFFSHORE SERVICES PROJECTS

    OFFSHORE SERVICES

    Taiwanese offshore pile load test project

    OFFSHORE SERVICES

    Manifold installation

    Leave a Reply